«MINUTES OF THE 127th FRAB MEETING HELD ON THURSDAY 23 June MARCH 2016 AT HM TREASURY Present: Katheryn Cearns (Chair) Russell Frith (observer) Andrew ...»

-- [ Page 1 ] --

MINUTES OF THE 127th FRAB MEETING HELD ON

THURSDAY 23 June MARCH 2016

AT HM TREASURY

Present: Katheryn Cearns (Chair) Russell Frith (observer)

Andrew Buchannan Larry Honeysett

Veronica Poole Gareth Caller

David Hobbs Vicky Rock

Bob Branson Andrew Baigent

Ruth Elliot Joanne McBurney

David Aldous On the phone: Anthony Appleton, Gawain Evans, Aileen Wright, Sarah Sheen (CIPFA) Secretariat: Michael Sunderland (FRAB Secretary) Apologies: Ron Hodges, Jason Dorsett, Derek Yule, Ian Carruthers, Neil Hartley AGENDA ITEMS (in order tabled)

1. Whole of Government Accounts

2. IFRS 15 Exposure Draft

3. IFRS 9 Exposure Draft

4. IFRS 16 Leases Update

5. CIPFA/LASSAC update

6. Any other business Item 1: Whole of Government Accounts Treasury introduced the paper highlighting key trends from the 2014-15 Whole of Government Accounts and a progress update on 2015-16. Publication of the 2014-15 WGA was expected at the end of March but delays in major components (e.g. Department for Education) resulted in publication at the end of May. Two qualifications were removed on 3G/4G income and the valuation of schools assets. The qualification on un-eliminated balances is expected to be removed for 2015the error has been less than £8 billion for two years running. The qualification on highways network assets is also expected to be removed following the change in accounting in the CIPFA/LASSAC Code of Practice.

There has been a significant reduction in the ‘front half’as the Treasury starts to apply the principles of simplifying and streamlining for WGA. The focus for 2015-16 will be on reviewing disclosures.

The Treasury is looking to improve the communications strategy to expand the audience and usage of the WGA data. The WGA team will also be operating an account manager approach to provide more tailored advice and support to departments and to head off recurring issues.

The WGA team are currently in the testing phase of the 2015-16 Data Collection Tool (DCT) and as such there is likely to be delay in the 2015-16 timetable. Treasury are discussing with the National Audit Office whether this will have any implications on the audit time table. The expectation is still to publish WGA 2015-16 at the end of March 2017.

The Chair asked how much information is needed from central government departments before Treasury can start the consolidation process. In the private sector, consolidation is often based on draft data which is updated as needed. The Treasury explained that they did not wait for all departments to start the consolidation process. Howeverdepartments prioritise the production of their own statutory accounts over completing the DCT which prevents the timetable from being accelerated.

The Chair also asked how the 3G/4G qualification was removed. Treasury explained that in light of the change in classification in ESA 10 and an assessment of the likely future treatment under IFRS 15, the decision was made to change the treatment now, still applying IAS 18, thus removing the qualification.

Kate Mathers recognised progress is being made to improve WGA and the NAO were very supportive on the direction of travel and efforts made to raise the prominence of the accounts.

There is a PAC hearing in July on the government’s balance sheet which would be another opportunity to raise the profile of the accounts. Kate Mather said she had seen increased interest in government accounts from parliamentarians.

Vicky Rock raised the question of how the account could be better used, including the dataset behind it which has been collated over several years. The IFRS 16 paper shows some usages but she called for any reflections on where the Treasury could go further. Andrew Baigent said it would be worth reflecting on the practical uses of WGA. Within Health, there has been an increased interest from Ministers in the clinical negligence provisions resulting in more focus on the value for money aspects and looking more long term at how the provision can be reduced. The Treasury stated that the OBR will be producing a fiscal risks report and may look at the Whole of Government Accounts.

The Board should be aware that the OBR is looking to consult publically on the potential scope of the fiscal risks report.

David Hobbs asked whether there were any plans to audit the reconciliation between IFRS and the National Accounts. The Chair stated that as the reconciliation was in the front half, it was not subject to an audit opinion but was reviewed for consistency with the financial statements. In the private sector there was more emphasis on the front end reporting of non-statutory information and reconciling it back to the statutory information. Veronica Poole added there was well established practices in the private sector of disclosing reconciliations in the notes to the financial statements.

For example in the oil and gas sector where they disclose underlying performance measures. This provides users an indication of what management considers when looking at performance as well as the benefit of a full audit. Kate Mathers will discuss this point with the NAO WGA team.

The Chair thanked the WGA team and summarised that there was a lot of good work being undertaken. The Board would be interested in the feedback from the PAC hearing.





Item 2 and 3: IFRS 9 and IFRS 15 Exposure Drafts The Treasury introduced both Exposure Drafts. These Exposure Drafts were circulated for early comments out of meeting. Thanks was given to Ron Hodges and Department for Health for providing comments. The Exposure Drafts will be put out for consultation from 1 August to 30 September.

The proposals are to retain the existing IAS 39 interpretations when IFRS 9 is introduced and the existing treatment for revenue from taxes, duties, fines and penalties. No other adaptations or interpretations are proposed for either standard. The application of materiality is emphasised across both Exposure Drafts and will be an important judgment entities will have to make when applying the new standards and keeping in tune with the simplifying and streamlining agenda. To support implementation the Treasury plans to issue application guidance using examples from across government to assist with first time implementation and disclosures.

IFRS 15 Exposure Draft Andrew Baigent was supportive of the approach taken by the Treasury but had some concerns on the disclosure requirements, in particular what WGA may look for, as this may have material impacts on the way in which information is collated from the Heath sector.

Andrew Buchanan highlighted that preparers should not underestimate the implementation issues and challenges associated with IFRS 15. Even if the accounting did not have a significant impact, bodies found there was an increase in the amount of work required to produce the disclosures.

The Chair indicated it would be good to signpost in the Exposure Draft that work would be undertaken to provide examples of what disclosures would look like, not only for individual entities but also for the Whole of Government Accounts.

Vicky Rock stated it would be beneficial to provide some clarity in the overview on why the Standard was introduced by the IASB to provide some context to preparers that this was not a change merely imposed by relevant authorities. The Chair added that the five step process will be useful for new revenue items and whilst the change would be challenging, the implementation would be easier once the methodology was institutionalised.

Gawain Evans had no concerns on the Exposure Draft but was concerned on getting the application guidance soon to minimise issues raised later with auditors. Kate Mathers stressed that early engagement with auditors was encouraged.

The Chair highlighted that the IPSASB were looking at expanding the principles of IFRS 15 to nonexchange transactions i.e. through applying a modified IFRS 15 approach as IPSAS 23 was being revisited. A mirror image for non-exchange expenses was being considered as well. The projects were likely to take a long time and as such the Treasury should continue with its proposed approach rather than wait for IPSASB to complete their projects.

Anthony Appleton clarified that EFRAG provided advice rather than formal endorsement which is the job of the Commission. The ARC meeting was scheduled the following week so the Exposure Draft could be updated to reflect the latest position in the endorsement process before it is published.

Anthony also raised concerns of a potential inconsistency where CIPFA/LASAAC appeared to treat council tax as outside of scope of the Standard whereas Treasury were treating fees and levies as within scope. The Treasury Exposure Draft provided an example that legislation could be considered equivalent to a contract.

CIPFA explained that local authority taxes (ie council tax and non-domestic rates) were required by statutory prescription and were not a contractual arrangement, there was no agreement with a customer and no exchange of goods or services. Treasury explained that for departments, they act as an agent rather than a principal for taxes, and thus the revenue can reasonably be outside the scope of IFRS 15. In terms of levies it was considered that entities will need to undertake an assessment whether it is within the scope of IFRS 15 rather than automatically assume a classification. Anthony Appleton agreed and asked if para 4.7 could be expanded to distinguish general taxation from other sources of revenue to provide the other side of the equation.

David Hobbs requested that the ONS classifications should be kept in mind on determining definitions. The Treasury explained that the nature of IFRS as a micro level was a granular approach.

On contract by contract level was required but the Treasury didn’t see this as causing issues for the macro level ESA10 framework; the two are expected to remain broadly aligned. Bob Branson supported individual application as the Environment Agency has multiple revenue sources, including taxes that it can retain. It was appropriate that each one is assessed to determine the correct classification.

IFRS 9 Exposure Draft Similar to IFRS 15, the Chair stated the Exposure Draft would need to be updated for the upcoming ARC vote and add explanation on what had driven the change between IAS 39 and IFRS 9 referencing the financial crisis and the impairment methodology.

Andrew Buchanan asked for further emphasis that the change from an incurred loss model to an expected loss model would be a fundamental change in mind-set (para 4.13). Andrew raised concerns that para 4.15 could be read to suggest that the assessment on expected losses could be made solely on historical default rates. He explained that whilst historic data was a potential useful starting point, it needed to be overlaid with prospective data in order to meet the new criteria.

Andrew asked why there was a difference in the approach to hedge accounting where Treasury had kept the options open whereas CIPFA/LASAAC restricted it to just applying IFRS 9. Alison Scott explained the use of hedge accounting was very limited and therefore made sense to direct preparers to the new Standard. Andrew Buchanan raised concern that it might not be beneficial for WGA to have hedge accounting under both IFRS 9 and IAS 39 in use. The Chair asked whether there would be any material difference. The Treasury said it expects the WGA team to be a respondent to the Exposure Draft and will be able to highlight any concerns with the use of both IAS 39 and IFRS 9 by entities.

Veronica Poole added that it was unlikely that private sector entities with significant hedging would move towards the IFRS 9 approach as it would be costly to change systems which are considered well established under IAS 39. Andrew Buchannan agreed that where there was an established hedging strategy in place, there was no incentive to change. He raised the question on whether more of the public sector would be eligible to hedge under IFRS 9. The Treasury stated that under Managing Public Money hedging as a strategy was not actively encouraged as government had the ability to absorb the risk itself.

The Treasury asked whether there was any insights into the IASB macro hedging project and whether it could be changing. Andrew Buchanan stated that the IASB work on macro hedging was unlikely to progress quickly. The Chair asked who in government was using macro hedging. Vicky Rock said she was not aware of any that undertook macro hedging.

For the Exposure Draft it was decided that pros and cons for hedging under IAS 39 and IFRS 9 should be included. Questions should be asked to identify who in government undertakes macro hedging and whether entities had any concerns if Treasury mandated the use of IFRS 9.

Veronica Poole highlighted there were significant balances of receivables in the Whole of Government Accounts and recommended that the Treasury mandate the short cut method in IFRS 9 to reduce implementation issues. Veronica went on to say that it was easier to explain taking the impairment in one go rather than having to undergo constant assessment. Also where some departments only have receivables, it would make sense to use the short cut method. It was decided that a question would be raised to identify whether any entities had any issues with Treasury mandating the short cut method to see if it can help streamline implementation.

The Chair also asked for a paragraph to be added in both Exposure Drafts to show that relevant authorities were looking at the implementation issues in the private sector and considering any corresponding impacts in the public sector before the standards come into force.

The Treasury proposed to issue both Exposure Drafts for publication on 1 August. The Chair asked for the revised Exposure Drafts to be circulated to the board a week before publication for any final comments.

Item 4: IFRS 16 Leases The Treasury introduced the paper on IFRS 16 providing an analysis of the existing leases disclosed in the 2014-15 Whole of Government Accounts and initial consideration of transition. Future obligations on finance leases amount to £24 billion including interest – the majority sat with the Ministry of Defence. Future obligations on operating leases amount to £19.2 billion. The paper also provides a brief discussion on the misalignment between accounts, budgets and estimates if IFRS 16 were to be adopted.



Pages:   || 2 |


Similar works:

«Examples of refurbishment WP2 overview of refurbishment projects for the InoFin project Supported by the European Commission Composed by M. ten Donkelaar February 2007 Acknowledgement The data of the different refurbishment projects, shown in this document, is collected within Work Package 2 of the project “Innovative Financing of Social Housing Refurbishment in the Enlarged Europe” (InoFin). The European Commission supports this project under the Intelligent Energy Europe Programme. We are...»

«A New Focus on Groundwater–Seawater Interactions 334 (Proceedings of Symposium HS1001 at IUGG2007, Perugia, July 2007). IAHS Publ. 312, 2007. Effect of tidal fluctuations on contaminant transfer to the ocean IVANA LA LICATA1, CHRISTIAN D. LANGEVIN2 & ALYSSA M. DAUSMAN2 1 Dipartimento di Ingegneria Idraulica Ambientale e del Rilevamento (D.I.I.A.R.), Politecnico di Milano, I-20133 Milan, Italy ivana.lalicata@polimi.it 2 US Geological Survey, Florida Integrated Science Center, Fort Lauderdale,...»

«1 THE FULBRIGHT CENTER The Fulbright Center (the binational Fulbright Commission in Helsinki, Finland) is a service organization that specializes in cultural exchange between Finland and North America. The Center administers grant programs and provides advising, training and information services for students, researchers and working professionals. The ASLAFulbright program was established in 1949, and the year 2016 marks the 64th anniversary of the first Finnish grantees going to the U.S. The...»

«Board of Governors Meeting: September 16, 2009 Item: C2 Wilfrid Laurier University BOARD OF GOVERNORS Minutes of the Meeting Held Thursday, June 18, 2009, Brantford Campus, Carnegie Building 2 to 6 p.m. Present: Ms. B. Harris (chair), Mr. M. Alkier, Mr. S. Aslam, Dr. M. Blouw, Dr. C. Bricker, Dr. M-L Byrne, Mr. C. Canally, Mr. M. Certosimo, Mr. J. Champagne, Ms. M. D'Alton, Ms. J. Fisk, Ms. J. Haalboom, Ms. S. Hamilton Mr. D. Horman, Ms. P. Krajewski, Mr. T. Martin, Prof. J. McCutcheon, Mr. G....»

«Loek Dijkman NDERS ONDERNEMEN 50 JAAR ANDER R ANDERS ONDERNEMEN 50 JAAR ON NDERS ONDERNEMEN 50 JAAR ANDER AR ANDERS ONDERNEMEN 50 JAAR AN 0 JAAR ANDERS ONDERNEMEN 50 JAA EN 50 JAAR ANDERS ONDERNEMEN 50 NEMEN 50 JAAR ANDERS ONDERNEME DERNEMEN 50 JAAR ANDERS ONDERN ONDERNEMEN 50 JAAR ANDERS ONDE DERS ONDERNEMEN 50 JAAR ANDERS AR ANDERS ONDERNEMEN 50 JAAR AN 0 JAAR ANDERS ONDERNEMEN 50 JAA EN 50 JAAR ANDERS ONDERNEMEN 50 NEMEN 50 JAAR ANDERS ONDERNEME DERNEMEN 50 JAAR ANDERS ONDERN ONDERNEMEN 50...»

«Masaryk University Faculty of Arts Department of English and American Studies English Language and Literature Tereza Indrová Spoken, Written and Computer-Mediated Communication: The Language of Online Discussion Forums Bachelor‟s Diploma Thesis Supervisor: Mgr. Jan Chovanec, Ph.D. I declare that I have worked on this thesis independently, using only the primary and secondary sources listed in the bibliography... Author‟s signature Acknowledgement I would like to thank to Mgr. Jan...»

«Identifying Old Trees and Forests IN EASTERN WASHINGTON by Robert Van Pelt Acknowledgements This guide is a companion to Identifying Mature and Old Forests in Western Washington (Van Pelt, 2007). It was conceived in response to the work of the Old Growth Definition Committee. The committee was convened at the request of the Washington State Legislature to map and inventory old growth forests on state trust lands managed by DNR. In the course of the committee’s work, the need became apparent...»

«09-4704-cr(L) To Be Argued By: 09-5149-cr(XAP) HARRY A. CHERNOFF United States Court of Appeals FOR THE SECOND CIRCUIT Docket Nos. 09-4704-cr(L), 09-5149-cr(XAP) UNITED STATES OF AMERICA, Appellee-Cross-Appellant, —v.— VIKTOR KOZENY, DAVID PINKERTON, Defendants, (caption continued on inside cover) ON APPEAL UNITED STATES DISTRICT COURT FROM THE SOUTHERN DISTRICT OF NEW YORK FOR THE BRIEF FOR THE UNITED STATES OF AMERICA (REDACTED) PREET BHARARA, United States Attorney for the Southern...»

«HIT and urgent open heart  surgery: a sticky situation Hematology Grand Rounds January 30, 2015 Melinda Biernacki, MD Faculty Discussant: David Garcia, MD Case presentation 57 year old man w/ ischemic cardiomyopathy and decompensated CHF undergoing evaluation  for LVAD as destination therapy. Presented 6/11 in AK with acute decompensated CHF due to ischemia. • – LHC 6/13: 100% LAD occlusion d/t in‐stent restenosis. Left circ...»

«Direction de la santé publique Pôle prévention et promotion en santé publique Dossier suivi par : Dr. Annie BURBAUD annie.burbaud@ars.sante.fr; Christophe CAILLIEREZ christophe.caillierez@ars.sante.fr; Téléphone : 05.57.01.46.39 Courriel : ars-alpc-pps@ars.sante.fr Bordeaux, le Appel à candidatures pour le développement d’une nouvelle structure de gestion des dépistages organisés des cancers en Gironde CAHIER DES CHARGES DE LA STRUCTURE DE GESTION Textes de référence Code de la...»

«Universidad Abierta Interamericana Facultad de Desarrollos e Investigación Educativos. Sede Rosario Campus Roca. Carrera: Profesorado Universitario para la Educación Secundaria y Superior. Tesina Título “Propuesta Educativa de Prevención ante enfermedades de transmisión sexual”, para adolescentes de Barrio Carenciado de la Zona Sur de la Ciudad de Rosario. Alumna : María Cristina Pérez. cristinaperez2209@hotmail.com Domicilio: Garibaldi 1278 – Rosario. Teléfono: 0341 155 715823...»

«Joint Interpretation Library Requirements to perform Integrated Circuit Evaluations Version 1.1 February 2013 Requirements to perform Integrated Circuit Evaluations Joint Interpretation Library This page is intentionally left blank Page 2/21 Version 1.1 February 2013 Joint Interpretation Library Requirements to perform Integrated Circuit Evaluations Table of contents 1 Rationale 2 Introduction 3 Required Knowledge and Skill 3.1. Overview 3.2. IC Design and Production Process 3.3. Smartcard...»





 
<<  HOME   |    CONTACTS
2017 www.abstract.dislib.info - Abstracts, online materials

Materials of this site are available for review, all rights belong to their respective owners.
If you do not agree with the fact that your material is placed on this site, please, email us, we will within 1-2 business days delete him.